multifamily project · New York City, NY
102 West 27 Street Manhattan, New York City, NY 10001
Multifamily General Building, Hvac/Mechanical work permitted February 19, 2025, with 2 permits through February 19, 2025, declaring $750,000 of work. Contractor on record: SPK/Lewis Construction LL.
Get a free email when a new permit is filed here
- $750K
- Project value
- 2
- Permits
- Feb 19
- First permit
- 97 days
- Application to issuemedian
What's being built
INTERIOR RENOVATION OF EXISTING AMENITY SPACE & NEW FURNITURE LAYOUT ON EXISTING TERRACE,LOCATED ON THE 2ND FLOOR. SCOPE LIMITED TO NON-STRUCTURAL PARTITION DEMOLITION, NEW FULL HEIGHTNON-STRUCTURAL PARTITIONS, NEW LAYOUT, LIGHTING & FINISHES. NO CHANGE I
Who is building at 102 West 27 Street Manhattan?
New York City permit records name SPK/Lewis Construction LL as the contractor on this project.
On file for this address
- A contractor phone number
- The property owner
One charge, nothing renews. Refunded in full if the record lacks what’s listed here.
Permits at 102 West 27 Street Manhattan
2 permits issued Feb 19 – Feb 19, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Dec 12 | #M01066775-S1-MS Mechanical Systems · Initial Permit installation of mechanical units Status: Signed-Off | SPK/Lewis Construction LL | $25K |
| applied Oct 17 | #M01066775-I1-GC General Construction · Initial Permit INTERIOR RENOVATION OF EXISTING AMENITY SPACE & NEW FURNITURE LAYOUT ON EXISTING TERRACE,LOCATED ON THE 2ND FLOOR. SCOPE LIMITED TO NON-STRUCTURAL PARTITION DEMOLITION, NEW FULL HEIGHTNON-STRUCTURAL PARTITIONS, NEW LAYOUT, LIGHTING & FINISHES. NO CHANGE I Status: Signed-Off | SPK/Lewis Construction LL | $725K |
Other projects in 10001
Commercial and multifamily, biggest first.
- 20 Hudson Yards ManhattanREMOVAL OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialBuilding· Structure Tone, LLC$52.5MJan 3
- 20 Hudson Yards ManhattanModification to existing HVAC systems including installation of commercial cooking and hood/duct system. Commercial kitchen on 5th floor. No change in use, egress or occupancy.commercialHVAC / Mechanical· Structure Tone, LLC$23.1MDec 26
- 11 Pennsylvania Plaza ManhattanGENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 15TH AND 16TH FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialBuilding, HVAC / Mechanical$21.9MOct 22
- 30 Hudson Yards ManhattanFiling herewith Interior renovation, construction of non-load bearing partitions, floors, ceilings and doors as per plans. No change to use, egress or occupancy.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Benchmark Builders LLC$20.6MFeb 20
- 66 Hudson Boulevard ManhattanHereby filing to construct interior partitions, ceilings and doors for for office fit out as shown on plans filed herewith. No change to use, occupancy or egress.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· JRM Construction MGMT LLC$20MSep 10
- 30 Hudson Yards ManhattanHEREWITH FILING ARCHITECTURAL RENOVATIONS FOR INTERIOR FITOUT OF 12TH FLR (MARKETING FLR 16) PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Structure Tone, LLC$19.4MFeb 13
More projects by SPK/Lewis Construction LL
In New York City, biggest first.
- 69-30 Austin Street QueensINTERIOR RENOVATION AT 4TH FL. NO CHANGE TO USE EGRESS NOR OCCUPANCY.commercialBuilding, Fire protection, HVAC / Mechanical· SPK/Lewis Construction LL$3.2MOct 30
- 1140 Amsterdam Avenue ManhattanGENERAL CONSTRUCTION/RENOVATION FOR FOR LEVEL 300 LIBRARY AS SHOWN HEREWITH. NO CHANGES TO EGRESS, OCCUPANCY OR USE.commercialBuilding, Fire protection, Plumbing· Manengeering Bureau Inc$3MOct 30
- 240 Mercer Street ManhattanFILING HEREWITH GENERAL CONSTRUCTION TO INCLUDE INTERIOR RENOVATIONS OF DORM ROOMS & COMMON SPACES FOR ADA COMPLIANCE AS PER PLANS.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· SPK/Lewis Construction LL$2.1MJul 1
- 51 Central Park West ManhattanInstallation of new finish flooring at first floor and mezzanine as shown on drawings. No change in use, egress or occupancy.commercialBuilding, HVAC / Mechanical· SPK/Lewis Construction LL$1.9MNov 5
- 75 3 Avenue ManhattanFiling herewith general construction to include interior renovation and minor demo as per plans.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Skinner Plmng & HTG Corp$1.5MFeb 4
- 540 East 76 Street ManhattanModifications of interior partitions and finishes as per plans.commercialBuilding, HVAC / Mechanical· SPK/Lewis Construction LL$1.2MJun 8