Commercial General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted November 20, 2025, with 13 permits through July 8, 2026. Contractor on record: First Standard Constr Inc.
Get a free email when a new permit is filed here
- n/a
- Project value
- 13
- Permits
- Nov 20
- First permit
- 742 days
- Application to issuemedian
What's being built
Multipoint Suspended Scaffold and monorail hoist system installation as per plans filed herewith. No change in use, egress or occupancy.
Who is building at 10 West 17 Street Manhattan?
New York City permit records name First Standard Constr Inc, Safepipe Plumbing Inc and Urban Masonry&Concrete Co as the contractors on this project, among 4 contractors in all.
On file for this address
- A contractor phone number
- The property owner
One charge, nothing renews. Refunded in full if the record lacks what’s listed here.
Permits at 10 West 17 Street Manhattan
13 permits issued Nov 20 – Jul 8, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jul 8 | #M00951254-Z3-SC Suspended Scaffold · Initial Permit Multipoint Suspended Scaffold and monorail hoist system installation as per plans filed herewith. No change in use, egress or occupancy. Status: Permit Issued | Urban Masonry&Concrete Co | — |
| applied Mar 19 | #M00951254-Z1-PMM Protection and Mechanical Methods · Initial Permit INSTALLATION AND USE OF TEMPORARY KNUCKLEBOOM AS PER PLANS FILED HEREWITH. NO CHANGE IN USE EGRESS, OR OCCUPANCY. Status: Permit Issued | Cast Contracting Inc | — |
| applied Dec 12 | #M00951254-S6-EW-SP Standpipe · Initial Permit Sprinkler and Standpipe work in conjunction with NB Construction. Status: Permit Issued | Safepipe Plumbing Inc | — |
| applied Dec 12 | #M00951254-S6-EW-SD Sprinklers · Initial Permit Sprinkler and Standpipe work in conjunction with NB Construction. Status: Permit Issued | Safepipe Plumbing Inc | — |
| applied Aug 21 | #M00951254-S8-EW-SD Standpipe · Initial Permit Temporary standpipe in conjunction with NB # M00951254-I1. Status: Permit Issued | Safepipe Plumbing Inc | — |
| applied Dec 22 | #M00951254-S4-PL Plumbing · Initial Permit Plumbing work in conjunction with new building construction Status: Permit Issued | Safepipe Plumbing Inc | — |
| applied Jan 31 | #M00951254-S7-PL Plumbing · Initial Permit Application filed for underground plumbing work as per plans. Status: Permit Issued | Safepipe Plumbing Inc | — |
| applied Nov 25 | #M00951254-S9-FO Foundation · Initial Permit NYC DEVHUB: Underpinning scope of work to support previous foundation element on property as part of the SOE Design.Filed in conjunction with NB: M00951254-I1, FO: M00951254-S1, SOE: M00951254-S3 Status: Signed-Off | First Standard Constr Inc | — |
| applied Nov 14 | #M00951254-S1-FO Foundation · Initial Permit Foundation work in conjunction with new building construction. Status: Signed-Off | First Standard Constr Inc | — |
| applied Jan 12 | #M00951254-S3-SE Support of Excavation · Initial Permit SOE work in conjunction with new building construction. Soil retention pier scope of work (underpinning) filed under M00951254-S9. Status: Signed-Off | First Standard Constr Inc | — |
| applied Nov 14 | #M00951254-S2-ST Structural · Initial Permit Structural work in conjunction with new building construction. Status: Permit Issued | First Standard Constr Inc | — |
| applied Dec 13 | #M00951254-S5-MS Mechanical Systems · Initial Permit Mechanical work in conjunction with NB Construction. Status: Permit Issued | First Standard Constr Inc | — |
| applied Nov 9 | #M00951254-I1-GC General Construction · Initial Permit Dev.Hub Consultation 10/25/23. Application filed to erect 18 story new building. Status: Permit Issued | First Standard Constr Inc | — |
Other projects in 10011
Commercial and multifamily, biggest first.
- 408 West 15 Street ManhattanGENERAL CONSTRUCTION ON THE CELLAR, 1ST TO 4TH FLOOR AND ROOF AS PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.commercialBuilding· Structure Tone, LLC$22.4MApr 17
- 122 5 Avenue ManhattanInterior partial demo and reconstruction of existing floor slabs on the 3rd - 5th floors. Demo of existing partitions and doors. Proposed stair and enclosure to be filed under…commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· JT Magen & Company Inc$19.2MOct 16
- 550 West 20 Street ManhattanFILING HEREWITH FOUNDATION WORK FOR BUILDING CONSTRUCTION AS PER PLANS.commercialBuilding$13.1MNov 5
- 418 West 21 Street ManhattanSEABURY HALL - REMOVAL AND INSTALLATION OF MECHANICAL DUCTWORK AND EQUIPMENT.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Consigli Construction Co$12.9MMay 7
- 134 West 18 Street ManhattanINTERIOR AND EXTERIOR RENOVATIONS ON FLOORS 01-03, FAC & ROF FOR NEW THEATRICAL STUDIO & OFFICES. HORIZONTAL EXTENSION AT 1ST FLOOR. VERTICAL EXTENSION AT 3RD FLOOR.commercialBuilding, Elevator, HVAC / Mechanical, Plumbing· Yorke Construction Corp$9.1MJan 9
- 111 8 Avenue ManhattanINSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Nucor Construction Corp$7.5MSep 14
More projects by First Standard Constr Inc
In New York City, biggest first.
- 199 North 5 Street BrooklynCONVERTING AN EXISTING 2-STORY COMMUNITY FACILITY TO A 13-FAMILY RESIDENTIAL BUILDING VERTICAL AND HORIZONTAL ADDING 3 FLOORS AS PER PLANS.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Onng Inc$5.2MOct 6
- 44 West 8 Street ManhattanMECHANICAL WORK IN CONJUNCTION WITH CONSTRUCTION OF NEW MIXED USE BUILDING 6 STORIES + CELLAR. INSTALL SPLIT A/C SYSTEMS, TOILET, KITCHEN, DRYER, AND TRASH ROOM EXHAUST. INSTALL…commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· First Standard Constr Inc—Sep 22
- 16 Convent Avenue ManhattanSUPPORT OF EXCAVATION WORK AS PER PLANS FILEDcommercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Press Builders Inc—Aug 14
- 36-45 31 Street QueensSuspended Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy.multifamily· Urban Masonry&Concrete Co—Aug 14
- 227 West 19 Street ManhattanSTRUCTURAL WORK IN CONJUNCTION WITH NEW BUILDINGmultifamilyBuilding, Fire protection, HVAC / Mechanical· Roundsquare Builders,LLC—Apr 6