Commercial General Building, Electrical, Hvac/Mechanical work permitted November 21, 2024, with 11 permits through June 22, 2026, declaring $102,969,876 of work. Contractor on record: Brian Christopher Dupree Sr..
Get new commercial permits in New Orleans, free weekly email
INTERIOR RENOVATIONS TO MEETING ROOMS, PREFUNCTION SPACES, CORRIDORS AND PUBLIC LOBBIES IN PHASE 1 AND 2 IN THE CONVENTION CENTER
New Orleans permit records name Brian Christopher Dupree Sr., Steele-R Development and Pillar Building, LLC as the contractors on this project, among 6 contractors in all.
The property owner is included with Pro.
11 permits issued Nov 21 – Jun 22, newest first.
| Issued | Permit | Contractor | Value |
|---|
| applied Jun 9 | #26-17303-SERV Electrical Service / Circuit / Feeder · SERV This permit is for a planned outage and reconnect to perform maintenance and cleaning of the main switch gear for Phase 2 of the Convention Center. Meter's, 8039992 and 8039993. Status: Permit Issued | Brian Christopher Dupree Sr. | — |
| applied Nov 7 | #25-34995-RNVN Renovation (Non-Structural) · RNVN Replacing fixtures & devices in restrooms TCO for Hall A and Mezz on 2-25-2026 Status: Temporary Certificate Of Occupancy | Steele-R Development | $114K |
| applied Jul 31 | #25-23113-RNVN Renovation (Non-Structural) · RNVN Interior Renovation of existing Great Hall and Mezzanine Toilet Rooms. TCO issued for Hall A, Mezzanine, Boardroom, Office 4-12-26 Status: Temporary Certificate Of Occupancy | Steele-R Development | $1.1M |
| applied Jun 27 | #25-19610-HVAC Mechanical HVAC · HVAC Furnish and install one AHU chill water with nine VAVs, two exhaust fans, and one VFR system with 5 cassettes Status: Finaled | Pillar Building, LLC | $175K |
| applied Jun 24 | #25-19173-ERPR Electrical Repair / Replacement / Addition · ERPR Wire New Outlets, New Light Fixture's and Switches for new office lay out. Install 2 new electrical pannels Status: Finaled | Not published | $103K |
| applied Jun 25 | #25-19329-ERPR Electrical Repair / Replacement / Addition · ERPR Entergy Reconnect Permit for Planned outage for Maintenance of main switch gear. Meter # 8033806 Phase 3 of the facility. Status: Finaled | Brian Christopher Dupree Sr. | — |
| applied Jan 8 | #25-00730-RNVN Renovation (Non-Structural) · RNVN In an existing back-of-house office suite area on second (mezzanine) floor, demolish existing finishes, non-bearing interior walls, doors, finish ceilings, toilet room, and lighting; Build out a new Public Safety Office Suite with reconfigure walls, ceiling, electrical outlets, lighting, toilet… Status: Finaled | Not published | $575K |
| applied Jul 31 | #24-23529-ERPR Electrical Repair / Replacement / Addition · ERPR Entergy shutdown and reconnect of electrical service to Phase 1 Meter # 8033803. This is to perform maintenance on the main switch gear. After hours inspection to be performed by third party inspector. Status: Finaled | Brian Christopher Dupree Sr. | — |
| applied Mar 7 | #25-07105-ERPR Electrical Repair / Replacement / Addition · ERPR Modification of electrical work in Phase 1 & 2 of Convention Center. Status: Certificate Of Completion | Jonathan Stephen Frischhertz | $17.4M |
| applied Jan 7 | #21-00420-RNVN Renovation (Non-Structural) · RNVN Replace 4 Chillers 1 cooling tower 2 pump motors and add one cooling tower. Status: Closed | Gallo Mechanical LLC | $3M |
| applied Jun 30 | #23-17873-RNVN Renovation (Non-Structural) · RNVN INTERIOR RENOVATIONS TO MEETING ROOMS, PREFUNCTION SPACES, CORRIDORS AND PUBLIC LOBBIES IN PHASE 1 AND 2 IN THE CONVENTION CENTER Status: Permit Issued | Aecom Hunt | Broadmoor, A Joint Venture | $80.5M |