Get ProEvery project in every city · from $33/mo
Get Procommercial project · New Orleans, LA
Commercial General Building, Electrical, Hvac/Mechanical work permitted April 23, 2025, with 8 permits through May 27, 2026, declaring $35,097,029 of work. Contractor on record: Ryan Carl Orgeron.
The scope of this project consists of alteration of existing, the design, manufacturing, and installation of the mechanical and electrical systems of an automated package sorting system in an existing UPS package center. *NO USE OR OCCUPANCY- STATE FIRE MARSHAL APPROVAL IS REQUIRED PRIOR TO USE AND OCCUPANCY* Permit extended (2) 180 day periods to September 17, 2027
New Orleans permit records name Ryan Carl Orgeron, Copeland & Johns, Inc. and Western Industrial Contractors, Inc as the contractors on this project, among 6 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
8 permits issued Apr 23 – May 27, newest first.
| Issued |
|---|
In New Orleans, biggest first.
| Permit |
|---|
| Contractor |
|---|
| Value |
|---|
| applied May 26 | #26-15773-HVAC Mechanical HVAC · HVAC Install New HVAC equipment and associated ductwork. Status: Permit Issued | Not published | $3M |
| applied May 26 | #26-15775-FGAS Mechanical Fuel Gas · FGAS Install New Gas Pipe. Status: Permit Issued | Not published | $35K |
| applied May 8 | #26-14026-SERV Electrical Service / Circuit / Feeder · SERV A-1 Electrical Contractor Inc. has been contracted to Electrical Services for the UPS HUB Building at 5700 Morrison Rd. 125 new circuits and 3,000 amps Status: Permit Issued | Ryan Carl Orgeron | $1.5M |
| applied Sep 4 | #25-26966-RNVS Renovation (Structural) · RNVS UPS New Orleans HUB Modernization Main Building and addition Status: Permit Issued | Copeland & Johns, Inc. | $9.1M |
| applied Mar 11 | #25-06700-RNVN Renovation (Non-Structural) · RNVN The scope of this project consists of alteration of existing, the design, manufacturing, and installation of the mechanical and electrical systems of an automated package sorting system in an existing UPS package center. *NO USE OR OCCUPANCY- STATE FIRE MARSHAL APPROVAL IS REQUIRED PRIOR TO USE… Status: Permit Issued | Western Industrial Contractors, Inc | $20.6M |
| applied Jun 20 | #25-18804-FGAS Mechanical Fuel Gas · FGAS Provide gas piping to 10 unit heaters. Each unit heater is 90,000 BTUs Status: Finaled | Joseph Jude Luparello Jr | $74K |
| applied Jun 10 | #25-17749-SERV Electrical Service / Circuit / Feeder · SERV Install meter can, ct cabinet, mdp. Install lights. Status: Closed | Raymond Michael Luminais | $145K |
| applied Jan 17 | #25-02105-NEWC New Construction · NEWC Installation of a temporary modular building, including utility connections. There will be minor revisions to striping within existing pavement, as well as a very small amount of additional paving. *The addtional paving will require storwater management or waiver prior to obtaining a C/O* Status: Finaled | Perrier Esquerre' Contractors LLC | $580K |