Multifamily General Building, Electrical, Elevator, Hvac/Mechanical work permitted October 21, 2025, with 67 permits through July 16, 2026, declaring $2,205,149 of work. Contractor on record: McDonnel Group LLC.
Get new commercial permits in New Orleans, free weekly email
Air handlers including hoisting and setting, outside air units, split systems, condensing units, exhaust fans and ducts, unit heaters, automaticdampers, manual dampers, smoke and fire dampers, gravity relief systems, elevator pressurization, grills, registers, diffusers, motors, motorstarters (for equipment provided under this scope of work), vents, hangers, and all other items necessary. APTS 400-414 Details
New Orleans permit records name McDonnel Group LLC, Ronald Joseph Graci and Otis Elevator as the contractors on this project, among 4 contractors in all.
The property owner is included with Pro.
67 permits issued Oct 21 – Jul 16, newest first.
In New Orleans, biggest first.
| Issued | Permit | Contractor | Value |
|---|
| applied Jul 8 | #26-20134-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation 2640 Canal St Apt 300 Status: Finaled | Ronald Joseph Graci | $25K |
| applied Jun 3 | #26-16649-FGAS Mechanical Fuel Gas · FGAS New Gas Line Installation for DOAS unit on rooftop and need meter Status: Finaled | The McDonnel Group | $5K |
| applied Jun 24 | #26-18735-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation 20 new circuits and 125 amps for 2640 Canal St Apt 215 Status: Finaled | Ronald Joseph Graci | $25K |
| applied Jun 16 | #26-17941-SERV Electrical Service / Circuit / Feeder · SERV Electrical for unit noted above Status: Finaled | Not published | $25K |
| applied May 7 | #26-13901-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation 20 new circuits 125 amps Status: Finaled | Not published | $25K |
| applied May 7 | #26-13897-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Closed | Not published | $25K |
| applied Mar 24 | #26-08852-MOVG Moving Equipment · MOVG Furnish and Install One Traction Elevator Status: Finaled | Otis Elevator | — |
| applied Feb 24 | #26-05426-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05429-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05431-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Permit Not Required | Not published | $25K |
| applied Feb 24 | #26-05420-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05435-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05399-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05413-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05416-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05422-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05424-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Feb 24 | #26-05423-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 25 | #25-36671-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36662-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 26 | #25-36893-HVAC Mechanical HVAC · HVAC Air handlers including hoisting and setting, outside air units, split systems, condensing units, exhaust fans and ducts, unit heaters, automaticdampers, manual dampers, smoke and fire dampers, gravity relief systems, elevator pressurization, grills, registers, diffusers, motors, motorstarters (for… Status: Permit Issued | Ben Mcdonnel | $50K |
| applied Oct 31 | #25-27111-HVAC Mechanical HVAC · HVAC Air handlers including hoisting and setting, outside air units, split systems, condensing units, exhaust fans and ducts, unit heaters, automaticdampers, manual dampers, smoke and fire dampers, gravity relief systems, elevator pressurization, grills, registers, diffusers, motors, motorstarters (for… Status: Finaled | Not published | $2M |
| applied Nov 26 | #25-36885-FGAS Mechanical Fuel Gas · FGAS GAS line installation-All gas piping, regulators, valves, fittings, and other accessories per code and contract documents. (ROOFTOP) Status: Finaled | Not published | $25K |
| applied Nov 24 | #25-36667-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36683-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 24 | #25-36660-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36665-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36669-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36676-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36677-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 24 | #25-36680-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 24 | #25-36681-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 24 | #25-36682-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Meter Release | The McDonnel Group | $25K |
| applied Nov 24 | #25-36686-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Meter Release | Not published | $25K |
| applied Nov 24 | #25-36687-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 24 | #25-36688-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Closed | The McDonnel Group | $25K |
| applied Nov 5 | #25-34676-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 5 | #25-34680-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 5 | #25-34682-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 5 | #25-34686-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 5 | #25-34688-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 5 | #25-34690-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Meter Release | Not published | $25K |
| applied Nov 5 | #25-34691-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | Not published | $25K |
| applied Nov 5 | #25-34717-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Meter Release | The McDonnel Group | $25K |
| applied Nov 5 | #25-34720-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 5 | #25-34723-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Permit Not Required | The McDonnel Group | $25K |
| applied Nov 5 | #25-34726-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work for individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 4 | #25-34589-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 4 | #25-34590-SERV Electrical Service / Circuit / Feeder · SERV Electrical work to individual apartment renovation Status: Finaled | The McDonnel Group | $25K |
| applied Nov 4 | #25-34591-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovations Status: Finaled | The McDonnel Group | $25K |
| applied Nov 5 | #25-34635-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Status: Finaled | Not published | $25K |
| applied Oct 24 | #25-33429-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33442-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | Not published | $25K |
| applied Oct 24 | #25-33412-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33379-SERV Electrical Service / Circuit / Feeder · SERV REQUIRED ELECTRICAL TO INDIVIDUAL APARTMENT RENOVATION Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such remedies… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33422-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33415-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33430-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33431-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | Not published | $25K |
| applied Oct 24 | #25-33434-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33436-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33438-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33439-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Finaled | The McDonnel Group | $25K |
| applied Oct 24 | #25-33440-SERV Electrical Service / Circuit / Feeder · SERV Required electrical work to individual apartment renovation Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such… Status: Permit Not Required | The McDonnel Group | $25K |
| applied Oct 1 | #25-30208-HVAC Mechanical HVAC · HVAC Air handlers including hoisting and setting, outside air units, split systems, condensing units, exhaust fans and ducts, unit heaters, automaticdampers, manual dampers, smoke and fire dampers, gravity relief systems, elevator pressurization, grills, registers, diffusers, motors, motorstarters (for… Status: Certificate Of Completion | Not published | $100K |
| applied Oct 8 | #25-27431-HVAC Mechanical HVAC · HVAC Air handlers including hoisting and setting, outside air units, split systems, condensing units, exhaust fans and ducts, unit heaters, automaticdampers, manual dampers, smoke and fire dampers, gravity relief systems, elevator pressurization, grills, registers, diffusers, motors, motorstarters (for… Status: Finaled | McDonnel Group LLC | $100K |
| applied Oct 17 | #25-32660-LOOP Construction Loop · LOOP Construction Loop Status: Finaled | Ronald Joseph Graci | $150 |