Commercial Electrical, Hvac/Mechanical, Sign work permitted February 19, 2025, with 6 permits through January 30, 2026, declaring $18,828 of work. Contractor on record: Tommie Gerald Zenon.
Get new commercial permits in New Orleans, free weekly email
Install a 60kW natural gas standby generator. Permit extended (1) 180 day period until August 19, 2026
New Orleans permit records name Tommie Gerald Zenon, Quattro Graphics, LLC and Gerald L.udwig Stawski Jr. as the contractors on this project, among 5 contractors in all.
The property owner is included with Pro.
6 permits issued Feb 19 – Jan 30, newest first.
| Issued | Permit | Contractor | Value |
|---|
In New Orleans, biggest first.
| applied Dec 3 | #25-37145-SATT Attached Sign · SATT A 3/4" deep, 181.7" wide, 28.9" tall sign on the front of the Building. Status: Finaled | Quattro Graphics, LLC | — |
| applied Sep 1 | #25-26485-ERPR Electrical Repair / Replacement / Addition · ERPR File an after-the-fact application to repair the wiring and conduits that feed the attached structure freezer containers at the rear of the building Status: Finaled | Gerald L.udwig Stawski Jr. | $1.9K |
| applied Feb 24 | #25-06038-EGEN Permanent Generator · EGEN Wiring of automatic transfer switch ATS and Natural Gas 60kW Generac generator for standby power. Status: Finaled | Tommie Gerald Zenon | $1.5K |
| applied Mar 11 | #25-07520-FGAS Mechanical Fuel Gas · FGAS Run a natural gas line to a 60kW standby generator Status: Finaled | Tommie Gerald Zenon | $2.5K |
| applied Jan 8 | #25-00724-ACCS Accessory Structure · ACCS "After the fact" Acessory structure permit for the containers. We recently informed that there is no permit on file which would have been from previous owner. We will have a licensed electrician come by tomorrow to check if everything is wired properly and file for an "After the fact" electrical… Status: Permit Issued | Jetstaw56 LLC | $1.9K |
| applied Jul 30 | #24-23469-ACCS Accessory Structure · ACCS Install a 60kW natural gas standby generator. Permit extended (1) 180 day period until August 19, 2026 Status: Finaled | Jay Dove Group, Inc. | $12.9K |