Multifamily General Building, Electrical, Elevator, Hvac/Mechanical work permitted May 29, 2025, with 55 permits through October 26, 2026, declaring $28,585,451 of work. Contractor on record: RNGD Builders LLC.
Get new commercial permits in New Orleans, free weekly email
Floor 1 of 4 which includes apartment Split System Heat Pumps (7) 2-Ton AHU in closet (1) 3-Ton AHU in closet (2) 4-ton AHU in closet, Community Room Split System (1) 5-Ton in closet and Maintenance Room Split System Heat Pump (1) 2-Ton in closet (All systems have condenser on the roof)
New Orleans permit records name RNGD Builders LLC, RNGD Builders LLC, Christopher Jake Laborde and Schindler Elevator as the contractors on this project, among 6 contractors in all.
The property owner is included with Pro.
In New Orleans, biggest first.
55 permits issued May 29 – Oct 26, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 22 | #26-31228-FGAS Mechanical Fuel Gas · FGAS Installation of gas line to generator for Winn Dixie Apartments at 1431 Saint Louis St. Status: Finaled | Contractor with Pro | $2.5K |
| applied Dec 8 | #25-37838-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Apr 8 | #26-10688-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Finaled | RNGD Builders LLC, Christopher Jake Laborde | $1.4M |
| applied Apr 8 | #26-10689-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Finaled | RNGD Builders LLC, Christopher Jake Laborde | $1.4M |
| applied May 18 | #26-14913-MOVG Moving Equipment · MOVG Elevator installation Status: Permit Issued | Schindler Elevator | — |
| applied Feb 20 | #26-05005-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Finaled | Not published | $1.4M |
| applied Feb 20 | #26-05004-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Meter Release | Not published | $1.4M |
| applied Feb 16 | #26-04630-HVAC Mechanical HVAC · HVAC Two Aaon RN‑040 DOAS rooftop units (5,000 CFM each) provide 100% outdoor air to all residential levels via vertical shafts. Units include variable‑capacity R‑454B compressors, microchannel condensers, SCR electric heat (60 kW), hot‑gas reheat, VFD supply fans, MERV‑8 filtration, and full… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Jan 22 | #26-02094-HVAC Mechanical HVAC · HVAC Floor 4 of 4 which includes Split System Heat Pumps. Apt. 404-406 & 411 have 2-Ton AHU in closet. Apt.401 has 3-Ton AHU in closet. Apt. 402, 403, 407-410 have 4-ton AHU in closet. (All systems have condenser on the roof) Status: Finaled | RNGD Builders, LLC | $1.4M |
| applied Jan 14 | #26-01263-HVAC Mechanical HVAC · HVAC Floor 3 of 4 which includes Split System Heat Pumps. Apt. 303-305, 306 & 311 have 2-Ton AHU in closet. Apt.312 has 3-Ton AHU in closet. Apt. 301, 302, 307-310 have 4-ton AHU in closet. (All systems have condenser on the roof) Status: Finaled | Not published | $1.4M |
| applied Jan 12 | #26-00948-HVAC Mechanical HVAC · HVAC Floor 2 of 4 which includes Split System Heat Pumps. Apt. 203-205, 206 & 211 have (5) 2-Ton AHU in closet. Apt.212 has (1) 3-Ton AHU in closet. Apt. 201, 202, 207-210 have (6) 4-ton AHU in closet. (All systems have condenser on the roof) Status: Finaled | RNGD Builders, LLC | $1.4M |
| applied Dec 24 | #25-39572-HVAC Mechanical HVAC · HVAC Floor 1 of 4 which includes apartment Split System Heat Pumps (7) 2-Ton AHU in closet (1) 3-Ton AHU in closet (2) 4-ton AHU in closet, Community Room Split System (1) 5-Ton in closet and Maintenance Room Split System Heat Pump (1) 2-Ton in closet (All systems have condenser on the roof) Status: Finaled | Charles K Sardi | $14M |
| applied Dec 8 | #25-37842-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Permit Issued | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37832-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37833-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37830-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37826-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37828-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37821-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37822-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37825-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37820-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37814-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37816-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37819-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37813-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37812-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37808-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37809-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37811-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37805-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37806-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37807-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37802-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37803-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37801-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law.… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37800-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37796-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37798-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37794-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37795-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37791-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37792-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37786-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37788-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37790-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Status: Meter Release | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37783-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37781-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37835-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37840-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37839-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Closed | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37837-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Dec 8 | #25-37836-SERV Electrical Service / Circuit / Feeder · SERV Install all electrical for unit. Includes 17 circuits with a 150 amp subpanel. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed… Status: Finaled | RNGD Builders LLC | $1.4M |
| applied Jun 18 | #25-18587-LOOP Construction Loop · LOOP Construction Loop Status: Finaled | Christopher Jake Laborde | $1.4M |
| applied Aug 21 | #23-23052-NEWC New Construction · NEWC Construction of 45 new apartment units in a 4 story, 48,000 SF building. This phase is a continuation of the Iberville Redevelopment Offsite Component under the Choice Neighborhood Initiative grant awarded to the City of New Orleans and HANO. Affordble Housing Development Status: Permit Issued | HCI Architecture Inc APC, RNGD | $11.8M |