Commercial General Building work permitted July 25, 2025, with 4 permits through September 23, 2026, declaring $755,150 of work.
Get new commercial permits near 20814 or Montgomery County MD, free weekly email
Revision 1,1 - The noted existing 600 amp disconnect/ main breaker is actually a 400 amp disconnect/main breaker. The solar design does not change. Solar main circuit will be connected to an existing second set of lugs on line side of main breaker.,Customer Wants To Use ePlansCustomer Wants To Use ePlans Interior work only,OME Solar will be installing to ballasted rooftop solar systems for the Stoneridge School located at 9101 Rockville Pike Bethesda Maryland. The Gym roofs system will be a Pepco net metered interconnect 178.2 KW system design and install to meet all regulatory codes and all…
Montgomery County MD’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
4 permits issued Jul 25 – Sep 23, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Apr 16 | #1154846 COMMERCIAL BUILDING · CONSTRUCT Construct new retaining wall to Private School, 2,013 Sq Ft. Status: Issued |
Commercial and multifamily, biggest first.
| $80K |
| applied May 29 | #1159737 COMMERCIAL BUILDING · CONSTRUCT CONSTRUCT 5 SEGMENTAL BLOCK RETAINING WALLS: WALL1 LENGTH 154'XHEIGHT 5'/WALL2 LENGTH 56'XHEIGHT 3.20'/WALL3 LENGTH 30'XHEIGHT 3'/WALL 4 LENGTH 37XHEIGHT 4.5'/WALL5 LENGTH 43'XHEIGHT 3.45' ALL HEIGHTS AT TALLEST POINT Status: Issued | Not published | $50.6K |
| applied May 16 | #1117304 COMMERCIAL BUILDING · INSTALL OME Solar will be installing to ballasted rooftop solar systems for the Stoneridge School located at 9101 Rockville Pike Bethesda Maryland. The Mater Center system will be a Pepco net metered interconnect 126 KW system design and install to meet all regulatory codes and all industry standards. Status: Finaled | Not published | $283K |
| applied May 16 | #1117311 COMMERCIAL BUILDING · ALTER Revision 1,1 - The noted existing 600 amp disconnect/ main breaker is actually a 400 amp disconnect/main breaker. The solar design does not change. Solar main circuit will be connected to an existing second set of lugs on line side of main breaker.,Customer Wants To Use ePlansCustomer Wants To Use… Status: Finaled | Not published | $342K |