Multifamily General Building work permitted December 19, 2024, with 3 permits through September 4, 2025, declaring $200,000 of work.
Get new commercial permits near 90019 or Los Angeles, free weekly email
Soft-Story seismic retrofit per LABC Chapter 93: SEISMIC UPGRADE TO AN EXISTING APARTMENT BUILDING AT THE GROUND LEVEL CONSISTING OF 4 BAYS ORDINARY MOMENT FRAME, WOOD SHEAR WALL AND UPDATE/REINFORCE TWO (2) EXISTING ORDINARY MOMENT FRAME. THE UPGRADE IS LIMITED TO THE GROUND FLOOR AREA ONLY.
Los Angeles’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
3 permits issued Dec 19 – Sep 4, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jun 25 | #24016-10002-09696 Bldg-Alter/Repair · Building SUPPLEMENTAL PERMIT TO 24016-10000-09696 - REVISE PLANS TO MATCH FIELD CONDITIONS. DOOR REMOVED DUE TO NOT BEING ABLE TO COMPLY WITH PULL SIDE CLEARANCES Status: Permit Finaled | Not published | — |
Commercial and multifamily, biggest first.
| applied Jan 13 |
#24016-10001-09696 Bldg-Alter/Repair · Building SUPPLEMENTAL PERMIT TO 24016-10000-09696 "REMODEL OF USE (E) 3-STORY APARTMENT"REVISE ARCHITECT OF RECORD. Status: Permit Finaled |
| Not published |
| — |
| applied Oct 7 | #24016-10000-32106 Bldg-Alter/Repair · Building Soft-Story seismic retrofit per LABC Chapter 93: SEISMIC UPGRADE TO AN EXISTING APARTMENT BUILDING AT THE GROUND LEVEL CONSISTING OF 4 BAYS ORDINARY MOMENT FRAME, WOOD SHEAR WALL AND UPDATE/REINFORCE TWO (2) EXISTING ORDINARY MOMENT FRAME. THE UPGRADE IS LIMITED TO THE GROUND FLOOR AREA ONLY. Status: Cofc Issued | Not published | $200K |