Commercial General Building work permitted February 11, 2025, with 28 permits through September 24, 2026, declaring $3,881,932 of work.
INTERIOR TENANT IMPROVEMENT TO FIRST AND SECOND STORY OF EXISTING OFFICE BUILDING
Los Angeles’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
28 permits issued Feb 11 – Sep 24, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jun 15 | #26016-30000-15870 Bldg-Alter/Repair · Building INTERIOR TENANT IMPROVEMENT TO FIRST AND SECOND STORY OF EXISTING OFFICE BUILDING Status: Issued | Not published | $1.8M |
| applied Jun 15 | #26030-30000-04252 |
Commercial and multifamily, biggest first.
Grading · Building
Grading for an open-air mechanical equipment pad supported by retaining walls with a screen wall surrounding the equipment. ***Mechanical equipment under separate permit***
Status: Issued
| Not published |
| $181 |
| applied Jun 15 | #26020-30000-01247 Nonbldg-New · Building Development of an open-air mechanical equipment pad supported by retaining walls with a screen wall surrounding the equipment. ***Mechanical equipment under separate permit*** Status: Issued | Not published | $120K |
| applied Jun 23 | #26016-30000-16607 Bldg-Alter/Repair · Building Tenant improvement of 1st & 2nd floors in existing office. Remodel of interior office spaces & restrooms. No change in use, occupancy Status: Issued | Not published | $291K |
| applied Apr 17 | #26016-30000-10201 Bldg-Alter/Repair · Building Interior renovation of existing office space. Work consisting of new non-load bearing partitions, new acoustic grid and tile, new & relocated lighting, new millwork, new finishes. Status: Issued | Not published | $188K |
| applied Mar 10 | #25016-10001-34534 Bldg-Alter/Repair · Building SUPPLEMENTAL PERMIT FOR PERMIT 25016-10000-34534 REVISION TO PREVIOUSLY APPROVED SMALL INTERIOR OFFICE TI PROJECT ON 4TH FLOOR OF EXISTING OFFICE BUILDING. ADDIING SWING DOORS TO PREVIOUSLY APPROVED TI PROJECT Status: Issued | Not published | $20K |
| applied Mar 23 | #26016-30000-07662 Bldg-Alter/Repair · Building Early start demolition of existing office space on levels 2 & 3 of an existing office building Status: Permit Finaled | Not published | $126K |
| applied Oct 9 | #25016-10000-30016 Bldg-Alter/Repair · Building NDC-2646, FOX Bldg 16|17,NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering… Status: Ok For Cofc | Not published | $501 |
| applied Mar 6 | #26016-10000-06148 Bldg-Alter/Repair · Building OFFICE TENANT IMPROVEMENT PROJECT ON 3RD FLOOR OF EXISTING BUILDING. NON-STRUCTURAL T.I., INCLUDING NEW INTERIOR NON-STRUCTURAL PARTITIONS, DOORS, AND FINISHES. AREA OF WORK FOR VALUATION PURPOSES: 1,189 SF. Status: Permit Finaled | Not published | $77.3K |
| applied Oct 14 | #25016-10000-30653 Bldg-Alter/Repair · Building NDC-2642, Fox Building 19, NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering… Status: Permit Finaled | Not published | $501 |
| applied Oct 9 | #25016-10000-30014 Bldg-Alter/Repair · Building NDC-2639, FOX Bldg 53NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements of… Status: Permit Finaled | Not published | $501 |
| applied Oct 9 | #25016-10000-30017 Bldg-Alter/Repair · Building (ePLAN) NDC-2647Fox Building 6 NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering… Status: Ok For Cofc | Not published | $501 |
| applied May 29 | #24016-10000-17092 Bldg-Alter/Repair · Building (ePLAN) NDC 2635 - Phase 2 Non-ductile concrete retrofit, Compliance with Division 95 of Building 29 and Building 222 (including Stages 3 & 4) Status: Cofc Issued | Not published | $70K |
| applied Dec 19 | #25016-10000-37132 Bldg-Alter/Repair · Building EXTERIOR ALTERATION TO EXISTING COMMERCIAL BUILDING TO INSTALL (1) Air Handler Unit (1) Condensing Unit and Duct Supports AT ROOF Status: Permit Finaled | Not published | $50K |
| applied Nov 21 | #25016-10000-34534 Bldg-Alter/Repair · Building TENANT IMPROVEMENT ON 4TH FLOOR OF EXISTING OFFICE BUILDING: ADD SLIDING DOORS TO SEPARATE EXISTING OPEN OFFICE SPACE. INCLUDES STRUCT. ALTERATION FOR SUPPORT OF THE SLIDING DOORS. Status: Permit Finaled | Not published | $45K |
| applied Sep 5 | #25016-30000-26911 Bldg-Alter/Repair · Building Interior TI of an existing 2632 SF cafe/restaurant on the ground floor. No new floor area or change of use/occupancy. Status: Permit Finaled | Not published | $171K |
| applied May 7 | #25016-10000-14154 Bldg-Alter/Repair · Building NDC-2637, FOX Bldg 95NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements of… Status: Ok For Cofc | Not published | — |
| applied May 7 | #25016-10000-14120 Bldg-Alter/Repair · Building NDC-2645, FOX Bldg 22,NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements… Status: Ok For Cofc | Not published | — |
| applied May 7 | #25016-10000-14155 Bldg-Alter/Repair · Building NDC 2644 - Fox Bldg 24.NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements… Status: Permit Finaled | Not published | $501 |
| applied May 7 | #25016-10000-14123 Bldg-Alter/Repair · Building NDC-2643, FOX Bldg 26NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements of… Status: Ok For Cofc | Not published | — |
| applied May 7 | #25016-10000-14152 Bldg-Alter/Repair · Building NDC-2648, FOX Bldg21, NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements… Status: Ok For Cofc | Not published | $501 |
| applied May 7 | #25016-10000-14153 Bldg-Alter/Repair · Building NDC-2636, FOX Bldg 221NDC Phase 2 - To verify and evaluate that the building, as constructed, meets the NDC Ordinance requirements. A detailed report or evaluation, including a structural analysis prepared by the engineer, demonstrated that the building complies with the engineering requirements… Status: Ok For Cofc | Not published | — |
| applied Mar 10 | #25016-30000-06554 Bldg-Alter/Repair · Building INTERIOR TI (NON STRUCTURAL) TO EXISTING OFFICE SPACE ON 2ND AND 3RD FLOORS OF BLDG 31. NO CHANGE OF USE, FLOOR AREA, OR OCCUPANCY. Status: Permit Finaled | Not published | $190K |
| applied Jun 20 | #25016-10000-19697 Bldg-Alter/Repair · Building T.I. ON 4TH FLOOR INCLUDING DEMOLITION OF INTERIOR PARTITIONS, DOORS, RAISED DLORRING, MILLWORK AND FINISHES INCLUDES NEW PARTITIONS AND DOORS, NEW ACT AND FYP BOARD CEILINGS, NEW PARISED FLOOR, AND NEW FINISHES, NO NOW AREA, NO CHANGE OF USE. Status: Issued | Not published | $462K |
| applied Aug 25 | #23016-30000-28797 Bldg-Alter/Repair · Building Interior T.I. to (e) parking garage building to restripe parking area on 3rd level to add 1standard stall, convert a van accessible stall with access aisle and a standard stall to accessible restrooms (520 sf) on 4th level, restripe to convert a compact stall to an accessible parking stall on 5th… Status: Permit Finaled | Not published | $31.2K |
| applied Nov 14 | #24016-30000-36486 Bldg-Alter/Repair · Building TI TO BUILDING 95 TO REPLACE EXISTING STEAM BOILERS, STRUCTURAL ANCHORAGE AND NEW ROOF OPENINGS TO (E) POWERHOUSE. NO CHANGES TO USE , FLOOR AREA, OR OCCUPANCY Status: Permit Finaled | Not published | $45K |
| applied Jan 16 | #25016-10000-01292 Bldg-Alter/Repair · Building NON STRUCTURAL T.I. ON FIRST FLOOR INCLUDING NEW PARTITIONS AND DOORS, DEMO OF EXISTING SUSPENDED CEILING, NEW GYP BOARD CEILING, NEW RAISED FLOOR, AND NEW FINISHES FOR ASSEMBLY ROOM 939 SF. Status: Permit Finaled | Not published | $94.7K |
| applied Nov 12 | #24016-30000-36198 Bldg-Alter/Repair · Building Add steel grating at bottom chord of (e) roof truss joists to build a mechanical maintenance platform at Technical Product Area above Stage B Status: Permit Finaled | Not published | $122K |