Commercial General Building, Electrical, Fire Protection, Roofing work permitted November 5, 2024, with 34 permits through October 8, 2026, declaring $2,002,182 of work. Contractor on record: City Service Electric Inc..
SELF-CERT 2019 CBRC: INTERIOR ALTERATIONS IN EXISTING OFFICE BUILDING ON 2ND FLOOR FOR A FULL FLOOR OFFICE TENANT. NEW PARTITIONS, DOORS, CEILINGS, LIGHTING, MILLWORK, AND FINISHES. ASSOCIATED ELECTRICAL AND MECHANICAL WORK AS PER PLANS. (OCCUPANCY GROUP B; TYPE 1A CONSTRUCTION)
Chicago permit records name City Service Electric Inc., Bear Construction Company and JC Anderson Inc as the contractors on this project, among 10 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
The contractor on 1 permit issued in the last 30 days is included with Pro.
See the contractorIn Chicago, biggest first.
34 permits issued Nov 5 – Oct 8, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 8 | #B200515182 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 10/8/2026. END DATE: 11/7/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT… Status: Active | Contractor with Pro | — |
| applied Sep 17 | #101086869 PERMIT - RENOVATION/ALTERATION SELF-CERT 2019 CBRC: INTERIOR ALTERATIONS IN EXISTING OFFICE BUILDING ON 2ND FLOOR FOR A FULL FLOOR OFFICE TENANT. NEW PARTITIONS, DOORS, CEILINGS, LIGHTING, MILLWORK, AND FINISHES. ASSOCIATED ELECTRICAL AND MECHANICAL WORK AS PER PLANS. (OCCUPANCY GROUP B; TYPE 1A CONSTRUCTION) Status: Active | JC Anderson Inc | $825K |
| applied Sep 16 | #101087624 PERMIT - RENOVATION/ALTERATION SELF-CERT 2019 CBRC: INTERIOR ALTERATION (LEVEL 2) TO AN EXISTING FIRST FLOOR OFFICE SPACE FOR A PROPOSED TENANT AMENITY CONFERENCE CENTER AS PER PLANS. WORK TO INCLUDE DEMOLITION OF NON-LOAD BEARING PARTITIONS, NEW PARTITIONS, DOORS AND HARDWARE, CEILINGS, LIGHTING, MECHANICAL, ELECTRICAL, AND… Status: Active | Bear Construction Company | $655K |
| applied Aug 31 | #B200509811 PERMIT – EXPRESS PERMIT PROGRAM · Communication Equipment ALTERATION OF EXISTING COMMUNICATION EQUIPMENT. ALTERATION OF 0 BOXES AND EQUIPMENT ON 1 TOWERS / STRUCTURES. LOCATION: MODIFICATION TO EXISTING ANTENNAS ON ROOF PER PLAN. Status: Active | Heights Tower Service, Inc. | $50K |
| applied Sep 2 | #B200510092 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 9/2/2026. END DATE: 10/2/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Aug 6 | #B200481758 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 8/6/2026. END DATE: 9/5/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Jul 9 | #B200478009 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 7/9/2026. END DATE: 8/8/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Apr 22 | #B200467389 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 5/1/2026. END DATE: 5/31/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Apr 22 | #B200467390 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 6/1/2026. END DATE: 7/1/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Apr 2 | #B200464765 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 4/2/2026. END DATE: 5/2/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Jan 6 | #B200455389 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 1/6/2026. END DATE: 2/5/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Jan 6 | #B200455390 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 2/1/2026. END DATE: 3/3/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Jan 6 | #B200455391 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 3/1/2026. END DATE: 3/31/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Active | City Service Electric Inc. | — |
| applied Dec 9 | #B200453588 PERMIT – EXPRESS PERMIT PROGRAM · Administrative Change FOR PERMIT B200411507: REPLACEMENT GENERAL CONTRACTOR. NEW CONTRACTOR(S) LISTED UNDER "OTHER APPLICANTS AND CONTRACTORS" ON PERMIT CERTIFICATE. Status: Complete | Triad Associates, Inc. Dba Concordia-Triad | — |
| applied Nov 26 | #B200452468 PERMIT – EXPRESS PERMIT PROGRAM · Electrical Work LOW VOLTAGE/COMMUNICATION ELECTRICAL WORK. ALTER EXISTING OTHER. SPECIFIC LOCATION: IT ROOM AND ELECTRICAL ROOM. Status: Complete | Mzi Electric, Inc. | $19.2K |
| applied Sep 29 | #B200444531 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 11/1/2025. END DATE: 12/1/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT… Status: Active | City Service Electric Inc. | — |
| applied Sep 29 | #B200444540 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 12/1/2025. END DATE: 12/31/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT… Status: Active | City Service Electric Inc. | — |
| applied Sep 29 | #B200444530 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 10/1/2025. END DATE: 10/31/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT… Status: Active | City Service Electric Inc. | — |
| applied Jun 25 | #B200431471 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 9/1/2025. END DATE: 10/1/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Jun 25 | #B200431470 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 8/1/2025. END DATE: 8/31/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Jun 25 | #B200431461 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 7/1/2025. END DATE: 7/31/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Apr 22 | #B200418707 PERMIT – EXPRESS PERMIT PROGRAM · Fire Alarm System FIRE ALARM: MODIFICATION OF EXISTING SYSTEM. ASSOCIATED BUILDING PERMIT:101063132. AFFECTS: 0 DWELLING UNITS; 1 NON-RESIDENTIAL UNITS. HIGH-RISE BUILDING: YES. VOICE COMMUNICATION: YES. SPECIAL LOCKING: NO. MONITORING TYPE: SUPERVISING STATION . SPECIFIC LOCATION: 7TH FLOOR. Status: Suspended | G S Electric | — |
| applied Mar 19 | #B200417759 PERMIT – EXPRESS PERMIT PROGRAM · Electrical Work LOW VOLTAGE/COMMUNICATION ELECTRICAL WORK. INSTALL DATA/VIDEO. SPECIFIC LOCATION: LOW VOLTAGE ELECTRICAL ON 7TH FLOOR. Status: Complete | Usdata Comm | $18.8K |
| applied Mar 17 | #B200417287 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 4/1/2025. END DATE: 5/1/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Mar 17 | #B200417290 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 5/1/2025. END DATE: 5/31/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Mar 17 | #B200417291 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 6/1/2025. END DATE: 7/1/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Feb 11 | #101063162 PERMIT - RENOVATION/ALTERATION SELF-CERT 2019 CBRC: INTERIOR ALTERATIONS IN EXISTING OFFICE BUILDING ON 7TH FLOOR, OFFICE SUITE 725. NEW PARTITIONS, PLUMBING VENTILATION AND ELECTRICAL WORK AS PER PLANS. (OCCUPANCY GROUP B; TYPE 1A CONSTRUCTION) Status: Suspended | Bear Construction Company | $404K |
| applied Jan 18 | #B200411507 PERMIT – EXPRESS PERMIT PROGRAM · Communication Equipment ALTERATION OF EXISTING COMMUNICATION EQUIPMENT. ALTERATION OF 0 BOXES AND EQUIPMENT ON 1 TOWERS / STRUCTURES. LOCATION: REMOVE/SWAP ANTENNAS AT EXISTING TELECOM ON ROOF. Status: Suspended | Ccsi Networks LLC | $30K |
| applied Jan 9 | #B200410725 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 2/1/2025. END DATE: 3/3/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Jan 9 | #B200410723 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 1/9/2025. END DATE: 2/8/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Jan 9 | #B200410727 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 3/1/2025. END DATE: 3/31/2025. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND… Status: Complete | City Service Electric Inc. | — |
| applied Nov 14 | #B200403410 PERMIT – EXPRESS PERMIT PROGRAM · Fire Alarm System FIRE ALARM: MODIFICATION OF EXISTING SYSTEM. ASSOCIATED BUILDING PERMIT:B200403410. AFFECTS: 0 DWELLING UNITS; 2 NON-RESIDENTIAL UNITS. HIGH-RISE BUILDING: YES. VOICE COMMUNICATION: YES. SPECIAL LOCKING: NO. MONITORING TYPE: SUPERVISING STATION . SPECIFIC LOCATION: 1ST & 11TH FLR PANEL REPLACE.… Status: Suspended | Or Construction Inc | — |
| applied Nov 5 | #B200404687 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 11/5/2024. END DATE: 12/5/2024. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT… Status: Complete | City Service Electric Inc. | — |
| applied Nov 5 | #B200404689 PERMIT – EXPRESS PERMIT PROGRAM · Monthly Maintenance Permit ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: BUSINESS. START DATE: 12/1/2024. END DATE: 12/31/2024. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT… Status: Complete | City Service Electric Inc. | — |