Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted August 17, 2026, with 7 permits through October 14, 2026, declaring $2,024,449 of work.
Demo and build back of customer experience center on 23rd floor. Includes new electrical, altered FP and Mech systems, new walls and finishes.
Charlotte’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
7 permits issued Aug 17 – Oct 14, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#COM-ELC-26-010129 Electrical · Construction LV - two new fire alarm devices and remove/reinstall 8 existing devices. This work is associated with construction permit COM-ALT-26-001311. Conduit pathways provided by others. Status: Inspection Phase |
Commercial and multifamily, biggest first.
| Not published |
| — |
#COM-ELC-26-010038 Electrical · Construction LV - INSTALL VIDEO WALL AND SEVERAL DISPLAY WITH SPEAKERS AND RACK IN THE IDF Status: Inspection Phase | Not published | — |
#COM-ELC-26-009076 Electrical · Construction LV - Remove 6 Existing Thermostats off the wall and re-install them after construction is completed. Also, includes relocation of (1) existing thermostat for FPB-23-1. Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000375 Fire · Construction Relocate heads to align with new wall layout and add 2 new heads to existing system. Status: Inspection Phase | Not published | — |
#COM-ALT-26-001311 Alteration · Construction Demo and build back of customer experience center on 23rd floor. Includes new electrical, altered FP and Mech systems, new walls and finishes. Status: Inspection Phase | Not published | $2M |
#COM-MEC-26-004177 Mechanical · Construction Relocating existing diffusers and extending branch duct run. Status: Inspection Phase | Not published | — |
#COM-ELC-26-008233 Electrical · Construction Include electrical demo, new LED fixtures, and new low voltage branch lines tied into existing panels. Status: Inspection Phase | Not published | — |