Commercial General Building, Plumbing work permitted February 21, 2025, with 2 permits through March 11, 2025, declaring $1,800,000 of work. Contractor on record: Ledge Creek Development, Inc..
( 807 PERRY AKA 809 PERRY - NATIONAL GRID SUBSTATION 30/12 RENOVATION ) EXTERIOR & INTERIOR RENOVATIONS TO EXISTING BUILDING TO BE USED FOR HOUSING SWITCHGEAR FOR NATIONAL GRID ELECTRICAL SUBSTATION #12 ( 3012 ). THE BALANCE OF THE NEW SUBSTATION COMPONENTS WILL BE CONSTRUCTED OUTSIDE THE ORIGINAL STRUCTURE ON THE SOUTH SIDE OF THE BUILDING FOLLOWING THE DEMOLITION WORK OF EXISTING SWITCHGEAR & TRANSFORMER ANNEXES DONE ON A SEPARATE DEMOLITION PERMIT. RENOVATIONS TO THE ORIGINAL STRUCTURE WILL INCLUDE NEW ROOF, MASONRY RESTORATION, NEW WINDOWS, DOORS, VENTS, NEW VENTILATION SYSTEM AND…
Buffalo permit records name Ledge Creek Development, Inc. and Frank Grandinetti SR as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
2 permits issued Feb 21 – Mar 11, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#GC24-9626811 GC · GENERAL CONTRACTOR ( 807 PERRY AKA 809 PERRY - NATIONAL GRID SUBSTATION 30/12 RENOVATION ) EXTERIOR & INTERIOR RENOVATIONS TO EXISTING BUILDING TO BE USED FOR HOUSING SWITCHGEAR FOR NATIONAL GRID ELECTRICAL SUBSTATION #12 ( 3012 ). THE BALANCE OF THE NEW SUBSTATION COMPONENTS WILL BE CONSTRUCTED OUTSIDE THE ORIGINAL… | Ledge Creek Development, Inc. | $1.8M |
#PLUM25-9634263 PLUMBING · PLUMBERS MASTER DEMO, 3 RD'S, 1 HB | Frank Grandinetti SR | — |