Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted February 12, 2025, with 7 permits through October 21, 2026, declaring $2,074,696 of work. Contractor on record: Louis Dicarlo.
Existing Carwash Level II Renovation & Addition. Demolish aged and worn interior. Demolish Wood framed offices at entrance. New interior layout w/ cmu & lgmf partitions, floor, equipment & MEP. New Roof Extension at entrance and exit to match & blend into existing steel beam framed roof. New exterior sub-grade precast wash sediment tanks (x4 Tanks) New entrance addition w/ enclosed mezzanine, exterior to be brick and match existing (400sf) New Site Retaining wall (Retention Pond) New Pay Booth (313sf) *** digeplan *** *** separate DPW permit(s) required for ROW work ***
Buffalo permit records name Louis Dicarlo, Todd Schmigel and Robin Cloy as the contractors on this project, among 6 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
Commercial and multifamily, biggest first.
7 permits issued Feb 12 – Oct 21, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#GC26-9693961 GC · GENERAL CONTRACTOR Existing Carwash Level II Renovation & Addition. Demolish aged and worn interior. Demolish Wood framed offices at entrance. New interior layout w/ cmu & lgmf partitions, floor, equipment & MEP. New Roof Extension at entrance and exit to match & blend into existing steel beam framed roof. New… | Contractor with Pro | $1.2M | |
#PLUM26-9705232 PLUMBING · PLUMBERS MASTER New sanitary and car wash primary and secondary drain lines below slab. Complete rough in of 1 toilet room, approx. 40 ft of trench drain. | Louis Dicarlo | $100K | |
#PLUM26-9703494 PLUMBING · PLUMBERS MASTER EXTERIOR SITE WORK ONLY: SANITARY/STORM/ WATER | Todd Schmigel | — | |
#HEAT26-9694036 HEATING · HEATING CONTRACTOR Installation of boiler, pumps, and associated accessories, exhaust fans, (1) 5Ton RTU, (3) Ductless Mini Splits, (2) Unit Heaters, associated ductwork and RGDs | Robin Cloy | $689K | |
#REP25-9653520 REP-PLANS · SPECIALTY CONTRACTOR Removal of Fire Suppression System as we meet Fire Codes Chapter: 23 and 57 of the IFC Analysis *** Digeplan *** | Kurt Juliano | $7K | |
#PKLT25-9645606 PARKINGLOT · SPECIALTY CONTRACTOR *** AKA 2590 Delaware *** mill 4700 sq ft - fill in low areas- resurface area. Rear portion re-pave only. Not associated with new addition/expansion. | John Valenti | $12K | |
#ELEC25-9632787 ELECTRICAL · MASTER ELECTRICIAN Electrical for remodel of an existing Delta Sonic Detail Shop including; Lights Plugs Equipment connections Replace (2) panel boards with like kind | Funke Electric Inc | $66.2K |
In Buffalo, biggest first.