RMDL-MARTIN H.S. RETROFIT CHILLERS, COOLING TOWERS AND PUMPS, TO INCLUDE M.E.P. 2021 iCodes/ 2020 NEC
Arlington’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
6 permits issued Jan 31 – Jul 15, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jun 24 | #FE-26-052788 FE · New AISD - MARTIN HIGH SCHOOL3313212 is the FDP folderRSN that was created when the folder was created. This is here so that if the ParentRSN gets changed to to "SP" it will be easy to find to reassociate it. Status: Issued | Not published | $50K |
#CP-25-006792 CP · New Construction CONSTRUCTION OF RETAINING WALL ONLY, NO M.E.P. 2021 iCodes. Status: Finaled |
| Not published |
| $175K |
| applied May 21 | #SI-26-042289 SI · Face Change AISD - MARTIN HIGH SCHOOL3302685 is the FDP folderRSN that was created when the folder was created. This is here so that if the ParentRSN gets changed to to "SP" it will be easy to find to reassociate it. Status: Finaled | Not published | $83.3K |
| applied Feb 24 | #CP-26-013910 CP · Remodel/Alterations/Repairs RMDL-MARTIN H.S. RETROFIT CHILLERS, COOLING TOWERS AND PUMPS, TO INCLUDE M.E.P. 2021 iCodes/ 2020 NEC Status: Issued | Not published | $2.8M |
| applied May 6 | #CP-24-049620 CP · New Construction NEWC AISD - M.H.S. SOFTBALL FIELD to include M.E.P. 2021 iCodes/ 2020 NEC Status: Finaled | Not published | $1.2M |
| applied Jan 24 | #FE-25-007452 FE · New Informational comments: retaining walls over 4-feet in height will require a separate permit. Status: Finaled | Not published | $300K |