Commercial General Building work permitted April 29, 2025, with 10 permits through April 7, 2026, declaring $1,075,000 of work. Contractor on record: Logan Whitaker.
Get new commercial permits near 87106 or Albuquerque, free weekly email
(Building Commercial) Commercial - Foundation Only (Issued) : Fastrax - Pile caps and slab for future mounted equipment.
Albuquerque permit records name Logan Whitaker, Jim Shaver and Joel Loes as the contractors on this project, among 6 contractors in all.
The property owner is included with Pro.
10 permits issued Apr 29 – Apr 7, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#BPC-2026-00198 Building Commercial (Building Commercial) Commercial - Alteration (Issued) : Scope added to project - X4 additional stainless steel pipes from chemical shed to tent structure.Permit #: BP-2023-35129 |
Commercial and multifamily, biggest first.
Status: Issued
| Joel Loes |
| $50K |
#BPC-2025-00630 Building Commercial (Building Commercial) Commercial - Foundation Only (Issued) : Fastrax - Foundation for future tanks/equipment and associated electrical grounding. Status: Issued | Logan Whitaker | $50K |
#BPC-2025-00058 Building Commercial (Building Commercial) Commercial - Foundation Only (Issued) : Construction of new foundations which will be used to support future installation of exterior pipe racking. Status: Issued | Michael Stefan | $50K |
#BPC-2025-00534 Building Commercial (Building Commercial) Commercial - Foundation Only (Issued) : Fastrax - Pile caps and slab for future mounted equipment. Status: Issued | Logan Whitaker | $700K |
#BPC-2025-00532 Building Commercial (Building Commercial) Commercial - Foundation Only (Issued) : Fastrax -Structural piles caps and concrete slab for future mounted equipment. Status: Issued | Logan Whitaker | $700K |
#BPC-2025-00533 Building Commercial (Building Commercial) Commercial - Foundation Only (Issued) : Fastrax - Pile caps and slab for future mounted equipment. Status: Issued | Logan Whitaker | $700K |
#BPC-2025-00403 Building Commercial (Building Commercial) Commercial - Foundation Only (Complete) : Permit drawings for new auger-cast piles foundations related to new, uncovered equipment pad. Status: Complete | Jim Shaver | $700K |
#BP-2024-42153 Building Commercial (Building Commercial) Commercial - Alteration (Complete) : Alterations to an existing space to create three (3) separate open-office areas, one (1) use-yet-to-be-determined area, three (3) accessible single-occupancy restrooms, and one (1) lactation room. Work includes new partition walls, doors,… Status: Complete | Gerald Gallegos | $325K |
#BPC-2025-00358 Building Commercial (Building Commercial) Commercial - Foundation Only (Issued) : FASTRAXPermit drawings for new auger-cast piles foundations related to new, uncovered equipment pad. Status: Issued | Berkel & Company Contractors Inc | $700K |
#BPC-2025-00323 Building Commercial (Building Commercial) Commercial - Foundation Only (Complete) : Fastrax- Permit drawings for new auger-cast piles foundations related to new, uncovered equipment pad. Status: Complete | Jim Shaver | $700K |