61,981 commercial and multifamily projects from New York City’s building permit records (11,164 of them permitted in the last 90 days), newest first, each with its address, scope, value and permits. The contractor is named once a project’s first permit is 30 days old (first permit on or before October 7, 2026); Pro shows it, with the phone number, the day the permit is issued.
Source: building permit records from New York City's Socrata open-data portal, checked daily. Data through . How we count
Page 1171 of 1240
- 38 West 90 Street ManhattanWSUR BLDG31_Roof Roofing Replacement and Rooftop Structure Renovation.multifamilyBuilding· Zoria Housing, LLC$338KNov 22
- 207 Bowery ManhattanFiling for removal of existing non-load bearing partitions inside office, removal of internal convenient stair and seal opening with same kind floor materials. No change in…commercialBuilding· Samfriends Devel & Const$30KNov 22
- 250 West 55 Street ManhattanModifications to mechanical ductwork and related piping as per plans. No change in use, egress or occupancy.commercialHVAC / Mechanical· Gannon Contracting LLC$340KNov 22
- 250 West 55 Street ManhattanModifications of partitions and office fronts as per plans. No change in use, egress or occupancy.commercialBuilding· Gannon Contracting LLC$300KNov 22
- 133 East 4 Street ManhattanINTERIOR RENOVATION FOR EXISTING RESTAURANT @ 1ST. FLOOR. NO CHANGE IN USE, EGRESS AND OCCUPANCY.multifamilyBuilding· Pan Link Construction Inc$46KNov 22
- 364 West 53 Street ManhattanSuspended Scaffolding out rigger system for facade restoration worksmultifamily· NY Wonder Construction Co—Nov 22
- 195 Broadway ManhattanMECHANICAL MODIFICATIONS TAKING PLACE ON 25TH FL CONSTRUCTION (26TH FL MARKETING) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.commercialHVAC / Mechanical· JT Magen & Company Inc$112KNov 22
- 3 Columbus Circle ManhattanFILED HEREWITH FOR INTERIOR RENOVATION TO EXISTING OFFICE AS PER PLANS. NO CHANGE TO USE EGRESS OR OCCUPANCYcommercialBuilding· Bldrs Group Inc$30KNov 22
- 111 West 19 Street ManhattanMechanical work for installing a new water-cooled packaged A/C unit AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.commercialBuilding, HVAC / Mechanical· Briggs Services LLC$210KSep 9
- 743 Madison Avenue ManhattanStructural modifications taking place on the cellar, 1-2nd floor as per plans filed herewith. No change in use, egress or occupancy a sper plans filed herewith.multifamilyBuilding· Vanguard Construction And$30KNov 22
- 480 Park Avenue ManhattanRenovation to apartment 2G, at 2nd floor. Partition, finish, fixture work. No change to use, egress or occupancy.multifamilyBuilding· 360 Prestige Contracting$120KNov 22
- 426 Columbus Avenue ManhattanReplacement of (2) rooftop air conditioning units on the roof. all existing ductwork to remain as is and not to be disturbed. No change in use egress and occupancy.commercialHVAC / Mechanical· Thermal Comfort Mech Corp$30KNov 22
- 75 Rockefeller Plaza Manhattangeneral construction, and associated stair work and slab infill between floors 8-9, as per plans filed herewith. no changes in use, egress or occupancy.commercialBuilding· RXR Construction Serv LLC$86.3KNov 22
- 11 West 18 Street ManhattanINSTALL AC UNITS PER PLANS.multifamilyHVAC / Mechanical· Urgent Air Solutions Inc$63.2KNov 22
- 102 West 75 Street ManhattanAPPLICATION IS FILED FOR INTERIOR ALTERATION TO EXISTING APARTMENT ON THE SECOND FLOOR. WORK INCLUDES REMOVAL AND REPLACEMENT OF INTERIOR FINISHES AND PARTITIONS. ALTERATION OF…multifamilyBuilding· Knockout Renovations SVCS$100KNov 22
- 60 East 106 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 1545 Madison Avenue ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 50 East 104 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 55 East 102 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 50 East 102 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 60 East 102 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 1465 Madison Avenue ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 65 East 99 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 110 East 99 Street ManhattanFISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decolamultifamily· Structual Presv System—Nov 22
- 156 2 Avenue ManhattanNew Cellar concrete slab on grade. No change to use, egress or occupancy.multifamilyBuilding· Dualcore Construction MGT$35KNov 22
- 177 East 123 Street ManhattanRemedy ECB violation 35684042X. To file structural ST work for temporary shoring of first floor concrete deck as required. No change in use, egress or occupancy under this…commercialBuilding· KNS Building Rest. Inc$25KNov 22
- 693 5 Avenue ManhattanModify Existing Air Conditioning, Outside Air & Toilet Exhaust Ductwork and Existing Mechanical Piping, Install VAV Boxes, Manual Dampers, Supply, Return & Exhaust Air Diffusers…commercialHVAC / Mechanical· Sentinel Builders, LLC$50KNov 22
- 235 East 10 Street ManhattanRENOVATE UNITS 1A,1B,1C,1D,1E,1G,1H,2A,2B,2D,2E,2F,2G,3A,3C,3E,3F,3G,3H,4A,4C,4E,4G,4H,&COMMON HALLWAY FROM CELLAR TO ROOF, INCLUDE REMOVING &INSTALLING NEW INTERIOR NON-LOAD…multifamilyBuilding, HVAC / Mechanical, Plumbing· T & T Plumbing Inc$1.4MFeb 6
- 217 West 19 Street ManhattanFiling for general construction work, including replacement of the roofing membrane and installation of new insulation and flashing above existing concrete decks (to remain). No…multifamilyBuilding· M&A Projects Restoration$35KNov 22
- 370 7 Avenue ManhattanMechanical work including installation of exhaust and make-up air system for commercial kitchen exhaust hood (type II), toilet exhaust, and split-system heat pump. No change in…commercialHVAC / Mechanical· Pristine Air Conditioning$76.9KNov 22
- 25 Columbus Circle ManhattanINSTALL NEW FAN FOIL UNITS AND NEW DUCT THROUGH OUT THE APARTMENT 62A AND 62F. NO CHANGE IN USE, EGRESS OR OCCUPANCY.multifamilyHVAC / Mechanical, Plumbing· Frankie PLBG & HTG L.L.C$195KApr 3
- 205 West 89 Street ManhattanModifications to the existing HVAC system on the (10th Floor) as per plans. No change to use, egress or occupancy.multifamilyHVAC / Mechanical· Renwood Interiors Corp$75KNov 22
- 5 Columbus Circle ManhattanPartial demolition of 15th and 18th floors. No change to use, egress or occupancy.commercialBuilding· Vema Group LLC$300KNov 22
- 345 East 93 Street ManhattanCOMBINATION OF APARTMENTS E, F & G ON THE 31ST FLOOR INTO ONE APARTMENT AS PER TPPN 3-97. GENERAL INTERIOR RENOVATION, INCLUDING PARTITION CHANGES AND NEW FINISHES. NO CHANGE IN…multifamilyBuilding· JR Interior Designs Inc$145KJan 14
- 1 Penn Plaza ManhattanPlumbing work on the 17th floor (Liuzzo) as indicated on drawings.commercialPlumbing· William C. Gerakaris P&H$26.6KNov 22
- 1 Penn Plaza ManhattanConstruction work on the 17th floor (Liuzzo) as indicated on drawings.commercialBuilding· Vanguard Construction And$326KNov 22
- 476 Broadway ManhattanFacade repairs. No change in egress, use or occupancy.multifamilyBuilding· Colgate Restoration Corp$29.4KNov 22
- 215 West 98 Street ManhattanREMOVAL AND INSTALLATION OF INTERIOR PARTITIONS, FLOORING, CEILINGS AND FINISHES. NO CHANGE IN USE, EGRESS OR OCCUPANCY.multifamilyBuilding· Peter Simon Restoration.C$350KNov 22
- 45 Rockefeller Plaza ManhattanStructural work associated with infill opening as per plans. No change in use, egress or occupancy.commercialBuilding· Rinnovo Construction, LLC$35KNov 22
- 211 Central Park West ManhattanMechanical work filed in conjunction with the renovation of an apartment 11K. Architectural and plumbing work as per plans. No change of use occupancy or egress.multifamilyHVAC / Mechanical· Ins Dynamics Inc$100KNov 22
- 132 East 35 Street ManhattanINTERIOR RENOVATION TO EXISTING APARTMENT 16E ON THE 16 FLOOR . REMOVE AND CONSTRUCT NEW PARTITION, UPGRADE OF KITCHEN AND BATHROOM,NEW FLOORING WERE REQUIRED. ALL AS PER PLAN NO…multifamilyBuilding· BSM Maintenance Corp$60KNov 22
- 60 East 42 Street ManhattanSPRINKLER/STANDPIPE MODIFICATIONS TAKING PLACE ON THE 50TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialFire protection· A + Sprinkler Corp$80.3KNov 22
- 457 West 57 Street ManhattanFACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE, EGRESS, OR OCCUPANCY.multifamilyBuilding· Tribute Restoration Inc$149KNov 22
- 241 West 4 Street ManhattanConvert existing multi family residential building into one family dwelling and renovate including the work at the roof level and at the rear yard. Remove fire escape at front…multifamilyBuilding, HVAC / Mechanical, Plumbing· R&S Elite Construction$1MAug 4
- 130 Greene Street ManhattanAPPLICATION FILED FOR INTERIOR RENOVATION OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES IN THE CELLAR AND ON THE 1ST FLOOR (CAUDALIE) AS PER PLANS FILED HEREWITH. NO…multifamilyBuilding, Fire protection, HVAC / Mechanical, Plumbing· Capital Improvement Servi$365KJan 30
- 1290 Avenue Of The Americas ManhattanModification to existing plumbing fixtures & sprinkler system as per plans filed herewith. No change in use, egress or occupancy under this application.commercialFire protection, Plumbing· Par Plumbing Co., Inc$189KDec 2
- 1290 Avenue Of The Americas ManhattanModification to existing plumbing fixtures & sprinkler system as per plans filed herewith. No change in use, egress or occupancy under this application.commercialFire protection, Plumbing· Par Plumbing Co., Inc$2MDec 2
- 1290 Avenue Of The Americas ManhattanModification to existing Sprinkler system and plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy under this application.commercialFire protection· Par Plumbing Co., Inc$66.6KDec 2
- 771 West End Avenue ManhattanProvide new heat pump with related ductwork and pipes. No Change in Use Egress or OccupancymultifamilyHVAC / Mechanical, Plumbing· Simple Choice PLBG And HT$130KNov 27
- 126 Prince Street ManhattanRenovation to existing commercial space to be occupied by Issey Miyake. Remove/install non load bearing partitions, flooring, ceilings, finishes and fixtures per plans filed…multifamilyBuilding· Mgi Designed Interiors$31.8KNov 22