How long commercial permits take in Fort Worth, by trade
Median days from application to issue and median declared value, commercial and multifamily permits issued August 1, 2026 – October 30, 2026.
| Trade | Permits | Median days to issue | Median declared value |
|---|---|---|---|
| Building | 650 | 62 | $200K |
| Electrical | 8 | 33 | — |
Counts only permits whose record includes an application date (700 of 700). Times depend on the city’s review track: express and over-the-counter trade permits often issue within days, new construction takes longer.
Most common commercial permit types
- Commercial Building Permit400
- Commercial Accessory Structure201
- Commercial Grading Permit70
- Residential Building Permit23
- Electrical5